So the first day back we got the cupboard and its framework removed

As can be seen in this photo the cupboard and the hull planking is now exposed to be cleaned and checked for any rot or damage that will have to be sorted out before any framework is pt back in place, the hull will  the paint will be painted before any framework is put in place once more. 





Just one of the ribs that was replace at sometime in the past and not done correctly as any rib needs to go past another rib by at least a foot to eighteen inches to keep its strength in the hull.




The same rib never made it to the beam shelf. So the job here will be to take the rib out down to the keel and then refit a complete rib from keel to the underside of the deck.





This is the port side with the rib in place and the porthole aft of the rib which is missing on the starboard side.





On the starboard side the planks have been replaced but the rib was not fitted correctly and the porthole was never refitted.



 

Comments

Popular posts from this blog

A big shout out for a cover to put over Chance so we can get on with the restoration of Chance.

Chance Autumn update

Next Job at the stern of Chance is going to be to remove the Rudder on Chance